In this fourth part of the four-part TNS Draft Program Plan, project engineering concerns are considered. The TNS Project is first broken down into the major time and functional periods of feasibility study, preconceptual design, conceptual design, and line item construction, while the elements of the project are organized into an administrative work breakdown structure. With the aid of these two classifying schemes, the project tasks are described in terms of schedule, estimated cost, type of funding, and proposed type of participant. The initial constraints of completion data, anticipated scientific inputs, and budget procedures are used to develop a two-phase project in which the facilities are authorized first and the device 2 years later. This specific mechanism is fundamental to the construction of the schedule and should be reconsidered when the completion and initiation dates are reformulated.