Joko Soeryanto
Published: 1992
Total Pages: 14
Get eBook
The result of the above efforts during the thirteen years of operation can be seen in the significantly improved plant flexibility and plant availability factor from76.70 % in 1978 to above 97 % since 1987 (expert during the imple-mentation of liquefaction unit capacity improvement project in 1990 and 1991, the plant availability slightly dropped to under 97%). Plant capacity has also increased to 130 % of the original design. This has been reflected by the successful achievement of each annual LNG shipment target. [Authors' abstract].